Core Protex Upgrade Work:

 

Audience: School Staff

 

Date : 14th August 2009

 

E2BN are carrying out upgrades of the Core filtering servers in the Data Centre in Cambridge. This is to take account of ageing hardware and capacity increases dictated by E2BN LA Internet link upgrades.

 

Impact: There will be no Internet access throughout that day. Access to Centrally Hosted systems and email will remain unaffected.

 

Programme of work:

Filter Servers: Add 1 x 50Mbs server

Cache Servers:  Remove 3 x older 50Mbs IBM e326 series. Install 3 x next generation IBM x3455 100Mbs capacity each.

Loadbalancers - replace x 2  with higher throughput models.

 

Final Array Capacity : 150Mbs + 50Mbs redundant - based on filter capacity.

Additional  requirements  =  1U rack space, 1 x 1Gbs switch port in correct VLAN,  1 x IP address in correct VLAN, 1 additional 240V power supply as per existing IBM servers
 